title | titleSuffix | description | ms.assetid | ms.prod | ms.technology | ms.manager | ms.author | author | ms.topic | ms.date | monikerRange |
---|---|---|---|---|---|---|---|---|---|---|---|
Configure Check-In Notes |
Azure Repos |
Configure Check-In Notes |
c7829273-4d53-412c-99d6-4944780ebc74 |
devops |
devops-code-tfvc |
jillfra |
sdanie |
steved0x |
conceptual |
08/10/2016 |
>= tfs-2015 |
Administrators of Team Foundation version control can add, configure, and remove check-in notes. Check-in notes settings are set in the Source Control Settings window. For more information about check-ins, see Check In Pending Changes.
Required Permissions
To complete this procedure, you must have the Edit project-level information permission set to Allow. For more information, see Permissions and groups reference.
- On the Team menu, click Project Settings, and then click Source Control.
- In the Source Control Settings dialog box, choose the Check-in Notes tab, and click Add.
- In the Add Check-in Note dialog box, in the Title box, either type the desired name (for example, Documentation Reviewer), or select an existing check-in note from the drop-down list.
- If you want the note to be mandatory for check-ins, select the Required on check-ins box.
- Click Add, to return to the Check-in Notes tab in the Source Control Settings window with the new check-in note title added.
- On the Team menu, click Project Settings, and then click Source Control.
- In the Source Control Settings dialog box, click the Check-in Notes tab.
- In the Required column, select the check-in notes that you want to designate as mandatory, and clear those that you do not want to designate as mandatory for the check-in process.
- On the Team menu, click Team Project Settings, and then click Source Control.
- In the Source Control Settings dialog box, click the Check-in Notes tab.
- Select the check-in note that you want to rename, and type a new name for it.
- On the Team menu, click Team Project Settings, and then click Source Control.
- In the Source Control Settings dialog box, select the Check-in Notes tab.
- Select the check-in note for which you want to change the order.
- Use the up and down arrow buttons to move the note to the desired order.
- Repeat process until all the check-in notes are in the order you desire. This ordering is reflected during the check-in process. For more information, see Using the Check In and Pending Changes Windows and Associate Check-in Notes with Changesets.
- On the Team menu, click Team Project Settings, and then click Source Control.
- In the Source Control Settings dialog box, click the Check-in Notes tab.
- Select the check-in note title that you want to remove, and click Remove.
Add Check-In Policies
Associate Check-in Notes with Changesets