Add a time-in-state measure to a Power BI report
Azure DevOps
Learn how to add a time-in-state measure to an existing Power BI report based on Analytics for Azure DevOps.
devops-analytics
kaelli
KathrynEE
sample
>= azure-devops-2019
10/04/2021

Calculate time-in-state for an existing Analytics view

[!INCLUDE version-gt-eq-2019]

The time a work item spends in a specific state or series of states is an important aspect for understanding efficiency. The Cycle Time and Lead Time Analytics widgets provide some measures of time-in-state. However, these widgets may not have the level of detail that you want.

This article provides a series of recipes using DAX calculations to evaluate time spent by work items in any combination of states. Specifically, you'll learn how to add the following calculated columns and one measure and use them to generate various trend charts. (All fields are calculated columns except the first one listed.)

  • Work Items Count (measure)
  • State Sort Order
  • Date Previous
  • Date Diff in Days
  • Is Last Day in State
  • State Time in Days
  • State Previous
  • State Changed
  • State Flow
  • State Change Count
  • State Change Count - Last Proposed
  • State Restart Time in Days
  • State Time in Days - In Progress

Important

  • When adding a calculated column or measure per the examples shown in this article, replace View Name with the table name for the Analytics view. For example, replace View Name with Stories - Last 30 days.

    Analytics view name table)
  • Analytics views do not support intra-day revisions. These examples have the most precision when using a Daily interval for the Analytics view.
  • All intra-day or intra-period (weekly/monthly) revisions are ignored by the calculations. This can result in unexpected results for specific scenarios like a work item showing no time "In Progress" when a work item is "In Progress" for less than a day.
  • Power BI default aggregations are used whenever possible instead of building measures.
  • Some calculations will include +0 to ensure that a numeric value is included for every row instead of BLANK. You may need to revise some of the calculated column definitions based on the workflow states used by your project. For example, if your project uses 'New", 'Active' and 'Closed' in place of 'Proposed', 'In Progress', and 'Completed'.

[!INCLUDE temp]

Add the Work Items Count measure

To simplify quickly generating reports, we designed Analytics views to work with default aggregations in Power BI. To illustrate the difference between a default aggregation and a measure, we start with a simple work item count measure.

  1. Load the Power BI pbix file associated with your view in Power BI Desktop. For details, see Connect with Power BI Data Connector.

  2. From the Modeling tab Calculations section of the ribbon, choose New Measure.

    [!div class="mx-imgBorder"]
    Power BI, Modeling tab, New Measure

  3. Replace the default text with the following code and then select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

    Work Items Count = 
    CALCULATE (
        COUNTROWS ( 'View Name' ),
        LASTDATE ( 'View Name'[Date] )
    )
    

    The Work Items Count measure uses the CALCULATE, COUNTROWS, and LASTDATE DAX functions that are described in more detail later in this article.

    [!NOTE]
    Remember to replace View Name with the table name for the Analytics view. For example, here we replace View Name with Stories - Last 30 days.

    [!div class="mx-imgBorder"]
    Power BI, Modeling tab, Work Items Measure

Understand the difference between a measure and a calculated column

Before describing the other functions you'll create, you'll want to understand the difference between a measure and a calculated column. Specifically, a measure always evaluates the entire table where a calculated column is specific to a single row.

Compare the Work Items Count measure with the default count aggregation based on the Work Item ID:

[!div class="mx-imgBorder"]
Count of Work Items

To get the correct count using a default aggregation, you apply the filter Is Current equals 'True'. This pattern of applying filters to a default aggregation will be the basis for many of the examples provided in this article.

[!div class="mx-imgBorder"]
Current count of Work Items

Add State Sort Order

By default, Power BI will show states sorted alphabetically in a visualization. It can be misleading when you want to visualize time in state and Proposed shows up after In Progress.

The following steps will help you resolve this issue.

  1. Verify that the State Category field is included in the Analytics view. This field is included in all default shared views.

  2. Choose New Column and replace the default text with the following code and then select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

    State Sort Order =  
    SWITCH (  
        'View Name'[State Category],  
        "Proposed", 1,  
        "InProgress", 2,  
        "Resolved", 3,  
        4  
    )  
    

    [!NOTE]
    You may need to revise the definition if you need more granularity than State Category provides. State Category provides correct sorting across all work item types regardless of any State customizations.

  3. Open the Data view and select the State field.

    [!div class="mx-imgBorder"]
    Data view, Select state field

  4. From the Column Tools tab (Data view), choose Sort by Column and then select the State Sort Order field.

    [!div class="mx-imgBorder"]
    Modeling tab, Sort by Column, Choose State Sort Order

The next step for calculating time-in-state requires mapping the previous interval (day, week, month) for each row of data in the dataset. It's a simple calculation using a calculated column. Typically, you would define this column as shown.

[!div class="tabbedCodeSnippets"]

Date Previous  = 
PREVIOUSDAY ( 'View Name'[Date] )

However, this approach has two main problems:

  • It works only for daily periods.
  • It doesn't handle gaps in the data. For example, if a work item is moved between projects.

To resolve these problems, the calculated column should find the previous day by scanning the Date field.

To add the Date Previous calculated column, from the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

Date Previous =
CALCULATE (
    MAX ( 'View Name'[Date] ),
        ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
        'View Name'[Date] < EARLIER ( 'View Name'[Date] )
)

This calculated column uses three DAX functions, MAX, ALLEXCEPT, and EARLIER, described in more detail later in this article. Keep in mind that, because this column is a calculated column, it's run for every row in the table and each time it's run it has the context of that specific row.

[!div class="mx-imgBorder"]
Table report, Title, Date, and Previous Date selected

Tip

From the context menu for the Date and Previous Date fields, choose Date (instead of Date Hierarchy) to see a single date for these fields.

Date Previous calculates the difference between the previous and current date for each row. With Date Diff in Days, we'll calculate a count of days between each of those periods. For most rows in a daily snapshot, the value will equal 1. However, for many work items that have gaps in the dataset, the value will be larger than 1.

Important

Requires that you have added the Date Previous calculated column to the table.

It's important to consider the first day of the dataset where Date Previous is blank. In this example, we give that row a standard value of 1 to keep the calculation consistent.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

Date Diff in Days =
IF (
    ISBLANK ( 'View Name'[Date Previous] ),
    1,
    DATEDIFF (
        'View Name'[Date Previous],
        'View Name'[Date],
        DAY
    )
)

This calculated column uses the ISBLANK and DATEDIFF DAX functions described later in this article.

Add Is Last Day in State

In this next step, we calculate if a given row represents the last day a specific work item was in a state. It supports default aggregations in Power BI with the next column we'll add, the State Time in Days.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

Is Last Day in State = 
ISBLANK (CALCULATE (
    COUNTROWS ( 'View Name' ),
        ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
        'View Name'[Date] > EARLIER ( 'View Name'[Date] ),
        'View Name'[State] = EARLIER ( 'View Name'[State] )
))

Add State Time in Days

The time that a work item spent in a specific state can now be calculated by summing the Date Diff in Days for each work item. This calculation will include all of the time spent in a specific state even if it has switched between states multiple times. It's possible to evaluate each row as a trend using Date or the latest information by using Is Last Day In State.

Important

Requires that you have added the Date Diff in Days and Is Last Day in State calculated columns to the table.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Time in Days = 
CALCULATE (
    SUM ( 'View Name'[Date Diff in Days] ),
    ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
    'View Name'[Date] <= EARLIER ( 'View Name'[Date] ),
    'View Name'[State] = EARLIER ( 'View Name'[State] )
) + 0

To demonstrate the State Time in Days column, the report below includes a chart (top) showing a single work item and the state it was in on each day. The second chart (bottom) shows the time that this work item has spent in each state over time. Notice that the state increases by one each day until it moves to the next state.

[!div class="mx-imgBorder"]
Trend of the Average Time in State

Create a trend chart based on State Time in Days

You can create a trend chart of an average time in state across all work items that were in that state on a given day using the State Time in Days calculated column and Date.

To demonstrate, the same visualization used above are updated to show an average across all work items. This representation can help build understanding of the amount of work in progress and how it impacts the overall time in state for the teams. This team has a pattern of committing to work that they aren't ready to start work on. The data for the following report is based on different data than the previous report.

[!div class="mx-imgBorder"]
Trend chart based on State Time in Days.

Add State Time in Days - Latest (Is Last Day In State)

When evaluating time-in-state for each work item in a table or when filtered by a field like Area Path, don't use the State Time in Days column in an aggregation. The aggregation will use the value for every day the work item was in the state. For example, if a work item was In Progress on Monday and moved to Completed on Thursday, the time-in-state is three days, but the sum of State Time in Days column is six days (1+2+3) which is clearly incorrect.

[!div class="mx-imgBorder"]
Add State Time in Days - Latest.

To resolve this issue, use State Time in Days and apply the filter Is Last Day In State equals 'True'. It eliminates all the historical data necessary for a trend and focuses instead on just the latest value for each state.

:::image type="content" source="media/StateTimeInDaysTableIsLast.png" alt-text="Use State Time in Days and apply the filter Is Last Day In State equals 'True'.":::

Add State Time in Days - In Progress

In the examples above, State Time in Days for a given work item is only counted when the work item was in that specific state. If your goal is to have the time-in-state for a given work item count towards an average continuously, you must change the calculation. For example, if we want to track the "In Progress" state, we add the State Time in Days - In Progress calculated column.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Time in Days - In Progress = 
CALCULATE (
    SUM ( 'View Name'[Date Diff in Days] ),
    ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
   'View Name'[Date] <= EARLIER('View Name'[Date]),
   'View Name'[State] = "In Progress"
) + 0

[!NOTE] You may need to revise the definition based on the workflow states used by your project. For example, the project used in the examples in this article use the 'In Progress' workflow state, however, Agile, Scrum, and CMMI processes typically use the 'Active' or 'Committed' states to represent work in progress. For an overview, see Workflow states and state categories.

The following image shows the effect of considering all time-in-state for every existing work item (shown left) versus only those work items in a specific state on a given day (shown right).

:::image type="content" source="media/TimeInStateActive.png" alt-text="Trend Comparison of the Average Time in State":::

State Time in Days trend of multiple states

Analyzing performance across multiple states is also possible using the "Continuous" pattern. However, this approach only works with a trend chart.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Time in Days - Working States = 
CALCULATE (
    SUM ( 'View Name'[Date Diff in Days] ),
    ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
   'View Name'[Date] <= EARLIER('View Name'[Date]),
   'View Name'[State] IN { "Committed", "In Progress" }
) + 0

[!NOTE] You may need to revise the definition based on the workflow states used by your project. For example, if your project uses 'Active' in place of 'Committed' or 'Proposed'.

The chart of the left shows combined average while the right-hand side shows each individual state.

[!div class="mx-imgBorder"]
Trend Comparison of multiple states

Get the State Time in Days- Latest for multiple states

You use the State Time in Days- Latest calculated column when creating a trend. Using a filter on the states, the State Time in Days column and Is Last Day in State provides a simple way to get the total time any work item or group of work items spent in a set of states.

[!div class="mx-imgBorder"]
Latest Time in States

Add State Previous

The Date Previous calculated column can also be used to look up past values such as previous state for each work item.

Important

Requires that you have added the Date Previous calculated column to the table.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Previous =
LOOKUPVALUE (
    'View Name'[State],
    'View Name'[Work Item Id], 'View Name'[Work Item Id],
    'View Name'[Date], 'View Name'[Date Previous]
)

This calculated column uses the LOOKUPVALUE, described later in this article.

The first LOOKUPVALUE parameter, 'View Name'[State], specifies to return the value of [State].

The next parameter, 'View Name'[Work Item Id], 'View Name'[Work Item Id], specifies that only rows with a matching work item ID as the current row should be considered.

And, the last parameter, 'View Name'[Date], 'View Name'[Date Previous], specifies that the date of the row being returned must have a [Date] that matches the [Previous Date] of the current row. In a snapshot, only one row can meet this criteria.

Using the State Previous column, we can flag the rows for each work item where a state transition has occurred. The Stage Changed calculated column you'll add has two special considerations:

  • Blank values of State Previous will be set to the Created Date of the work item
  • Creation of a work item is considered a state transition

Important

Requires that you have added the State Previous calculated column to the table.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Changed =
IF (
    ISBLANK ( 'View Name'[State Previous] ),
    'View Name'[Created Date].[Date] = 'View Name'[Date],
    'View Name'[State Previous] <> 'View Name'[State]
)

The calculated column is a boolean value that identifies whether the row is a state transition. By using the Not Equal To operator, you correctly catch rows where the previous state doesn't match the current state, which means the comparison returns True as expected.

With State Previous and State Changed calculated columns, you can create a column that will help illustrate the State Flow for a given work item. Creating this column is optional for the purposes of this article.

Important

Requires that you have added the State Previous and State Changed calculated columns to the table.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Flow = 
IF([State Changed], [State Previous], [State]) & " => " & [State]

Add State Change Count

As we move into the more complicated measures, we need to have a representation of the total number of state changes to compare the rows of a data for a given work item. We get the representation by adding a State Change Count calculated column.

Important

Requires that you have added the State Changed calculated column to the table.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Change Count = 
CALCULATE (
    COUNTROWS ( 'View Name' ),
    ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
    'View Name'[Date] <= EARLIER ( 'View Name'[Date] ),
    'View Name'[State Changed]
) + 0

Add State Change Count - Last Proposed and State Restart Time in Days

Calculating restarts, State Restart Time in Days, is a fairly complex calculation. The first step is to find the last time a work item was in a proposed state. Add the State Change Count - Last Proposed calculated column.

Note

You may need to revise the following definitions based on the workflow states used by your project. For example, if your project uses 'New' in place of 'Proposed'.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Change Count - Last Proposed = 
CALCULATE (
    MAX ( 'View Name'[State Change Count] ),
    ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
    'View Name'[Date] <= EARLIER ( 'View Name'[Date] ),
    'View Name'[State] = "Proposed"
)

Then, look further back to the past and see if there were some active states before this proposed state. Lastly, sum up all the days when work item was in active state before the last proposed.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Restart Time in Days = 
CALCULATE (
    SUM ( 'View Name'[Date Diff in Days] ),
    ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
    'View Name'[Date] <= EARLIER ( 'View Name'[Date] ),
    'View Name'[State Change Count] < EARLIER('View Name'[State Change Count - Last Proposed] ),
    'View Name'[State] <"Proposed"
) + 0

Since the State Restart Time in Days is updated for each row of data, you can either create a trend to evaluate rework across specific sprints or examine rework for individual work items by using 'Is Current'.

Add State Rework Time in Days

Similar to State Restart Time in Days, the State Rework Time in Days looks for the first time a work item was in the Completed state category. After that time, each day a work item spends in a state other than Completed, counts as rework.

From the Modeling tab, choose New Column and then replace the default text with the following code and select the :::image type="icon" source="media/checkmark.png" border="false"::: checkmark.

[!div class="tabbedCodeSnippets"]

State Rework Time in Days = 
IF (
    ISBLANK ( 'View Name'[State Change Count - First Completed] ),
    0,
    CALCULATE (
        SUM ( 'View Name'[Date Diff in Days] ),
        ALLEXCEPT ( 'View Name', 'View Name'[Work Item Id] ),
        'View Name'[Date] <= EARLIER ( 'View Name'[Date] ),
        'View Name'[State Change Count] EARLIER ( 'View Name'[State Change Count - First Completed] ),
        'View Name'[State] IN {"Completed", "Closed", "Cut" } = FALSE()
    ) + 0
)

[!NOTE] You may need to revise the above definition based on the workflow states used by your project. For example, if your project uses 'Done' in place of 'Closed'.

Additional information is provided in this section for the DAX functions used to create the calculated columns and measure added in this article.

  • CALCULATE: This function is the basis for nearly all examples. The basic structure is an expression followed by a series of filters that are applied to the expression.

  • COUNTROWS: This function, COUNTROWS ( 'View Name' ), simply counts the number of rows that remain after the filters are applied.

  • LASTDATE: We apply the LASTDATE filter to an expression, for example LASTDATE ( 'View Name'[Date] ), to find the newest date across all rows in the table and eliminate the rows that don't share the same date. With the snapshot table generated by an Analytics view, this filter effectively picks the last day of the selected period.

  • MAX: Returns the largest numeric value in a column, or between two scalar expressions. We apply MAX ( 'View Name'[Date] ), to determine the most recent date after all filters have been applied.

  • ALLEXCEPT: Removes all context filters in the table except filters that have been applied to the specified columns. Essentially, ALLEXCEPT ('View Name'', 'View Name'[Work Item Id]) reduces the rows in the table down to only the ones that share the same work item ID as the current row.

  • EARLIER: Returns the current value of the specified column in an outer evaluation pass of the mentioned column. For example, 'View Name'[Date] < EARLIER ( 'View Name'[Date] ), further reduces the data set to only those rows that occurred before the date for the current row that is referenced by using the EARLIER function. EARLIER doesn't refer to previous dates, it specifically defines the row context of the calculated column

  • ISBLANK: Checks whether a value is blank, and returns TRUE or FALSE. ISBLANK evaluates the current row to determine if Date Previous has a value. If it doesn't, the If statement sets Date Diff in Days to 1.

  • DATEDIFF: Returns the count of interval boundaries crossed between two dates. DATEDIFF subtracts Date Previous from Date to determine the number of days between them.

  • LOOKUPVALUE: Returns the value in result_columnName for the row that meets all criteria specified by search_columnName and search_value.